VALUE ENGINEERING ANALYSIS OF BEAM STRUCTURE ON GOLD FACTORY DEVELOPMENT PROJECT.
- Department of Civil Engineering, Adhi Tama Institute of Technology Surabaya, Indonesia.
- Abstract
- Keywords
- References
- Cite This Article as
- Corresponding Author
High demand in construction building materials certainly calls for material energy savings in order to secure project efficiency. The research was identity ineffectiv cost in structural works in a gold plant construction project. To prevent such inefficiency, value engineering method was adopted to secure cost efficiency. In tehe adoption of the value engineering analysis applied to beam structural works in a gold plant construction project, the researcher observed i item of job leading to loss cost the most, i,e. :beem structural works.The value engineering analysis application adopted was zero one method to generate a recomendation for beam strucutural works, i,e. :alternative 1, saving as much as IDR 157,675,945 or 8.44% of the total costs of beam structural works with a saving percentage by 1.54% of the total project costs.
- Barrie, Donald S. & Boyd C. Paulson Jr. 1984. AlihBahasa
- 1990. EdisiKedua. Jakarta : Erlangga
- Cahaya, Haposan I. T. dkk. 2017. PenerapanRekayasaNilai (Value Engineering) pada Pembangunan Gedung
- Kantor Pt. AsuransiJasa Indonesia di Kota PematangSiantar. Vol 6, No 1 (2017)
- Cahyadi, Hendra. 2017. BahanKuliahRekayasaNilai UM Palangkaraya.
- (umpalangkaraya.ac.id/dosen/hendracahyadi/wp-content/uploads/2017/09/Bahan) Accesed date 24/04/2018
- HidayatAchmadNurul, danArdianto Denny. 2011. RekayasaNilai Pembangunan GedungRusunawaAmabarawa.
- Semarang :FakultasTeknikUniversitasdiponegoro Semarang.
- Kaizen, Star Consulting. Analisis Pareto Langkah Demi Langkah.
- (https://smkberkaizen.wordpress.com/2011/09/18/analisis-pareto-langkah-demi-langkah/) Accesed date 11/08/2018
- Nurcahya, Hendra. (2016). EfisiensiBiayaPenggunaanBahanPenutupKolomdanListplankdenganMetode Value
- SkripsiTidakDiterbitkan. Surabaya : FakultasTeknikSipildanPerencanaanInstitutTeknologi
- Adhitama Surabaya.
- Project, Teknik Area. TabelBeratBesiPolos / Ulir. (http://komunitas-anak-teknik.blogspot.com/2010/10/tabel
- berat-besi-polos.html?m=1) Accesed date 05/09/2018
- Rahma, Diyardkk. (2017). Analisis Value Engineering denganMetode Zero-One padaProyek Pembangunan
- GedungLaboratoriumKomputerKampus 3 Universitas Ahmad Dahlan Yogyakarta. Skripsi. Semarang : Fakultas
- TeknikUniversitasdiponegoro Semarang.
- Rani, AHafnidar. (2015). Penerapan Value EngineeringPada Pembangunan JembatanPenggandaanMenuju
- Infrastruktur Yang Efektif, Efisien Dan Berkelanjutan.
- (https://mpinfrastruktur.blogspot.com/2015/10/valueengineering.html) Accesed date 16/10/2018
- Sastraatmaja, Soedradjat. 1984. Analisa Cara Modern AnggaranBiayaPelaksanaan. Bandung : Nova
- Seng Hansen, S.T., M.Sc. 2017. ManajemenKontrakKonstruksi. EdisiKedua. Jakarta :GramediaPustakaUtama.
- 2016. StudiPerbandinganBekistingKonvensionaldengan PCH (Perth Construction Hair)
- Utomo, AdiSetyo. 2016. AnalisisRekayasaNilai yang DiterapkanpadaPekerjaanDindingdanRangkaAtap di
- SDN Sumurwelut III Surabaya. Skripsitidakditerbitkan. Surabaya :FakultasTeknikSipildanPerencanaanInstitut.
- TeknologiAdhitama Surabaya.
[Siti Choiriyah and Kahfi Rizqi Wibowo. (2018); VALUE ENGINEERING ANALYSIS OF BEAM STRUCTURE ON GOLD FACTORY DEVELOPMENT PROJECT. Int. J. of Adv. Res. 6 (Dec). 1092-1097] (ISSN 2320-5407). www.journalijar.com
ITATS